Decoding Outputs: The Impact of Sequencing Activities on Project Schedules

Sequencing Activities is a crucial process in Project Schedule Management, which involves identifying and documenting dependencies among project activities. The outputs of this process serve as a roadmap for the project, guiding its execution and control.

This section explores the key outputs of sequencing activities, including project schedule network diagrams and updates to project documents. Project schedule network diagrams graphically represent the logical relationships among project tasks, highlighting potential risks and critical paths. Meanwhile, updates to project documents reflect changes in activity relationships, assumptions, constraints, and potential project risks, providing a dynamic view of the project's progress.

The process of sequencing activities interacts with other project management processes in several ways. For instance, the project schedule network diagrams feed into the development of the project schedule and the project management plan. Similarly, the updates to project documents can influence decision-making in areas such as cost management, risk management, and resource management. Ultimately, the outputs of sequencing activities contribute to the effective execution and control of the project, ensuring its successful completion.

Learning Objectives

  • Understand the purpose, structure, and types of information included in a project schedule network diagram.
  • Recognize the concepts of path convergence and divergence, and the associated risks in a project schedule network diagram.
  • Understand the role of activity attributes in describing sequences of events and relationships between activities.
  • Recognize the potential need for updating project documents such as activity attributes, activity list, assumption log, and milestone list during project management.
  • Understand how changes in relationships among project activities during sequencing may impact the project schedule, including scheduled dates for specific milestones.

Project Schedule Network Diagrams

A project schedule network diagram is a graphical representation of the logical relationships or dependencies among the project schedule activities. It can be produced manually or using project management software and can include full project details or consist of one or more summary activities.

A summary narrative often accompanies the project schedule network diagram to describe the basic approach used to sequence the activities. Any unusual activity sequences within the network should be fully described within the summary narrative.

Path convergence and divergence are two key concepts in a project schedule network diagram. Path convergence is represented by activities with multiple predecessor activities. For example, Activity I, which has more than one predecessor, is an example of path convergence. On the other hand, path divergence is represented by activities with multiple successor activities. Activity K, which has more than one successor, is an example of path divergence.

Activities that exhibit both divergence and convergence are at a higher risk because they are influenced by or can influence multiple activities. Understanding these concepts and being able to identify examples of path convergence and divergence in a project schedule network diagram is crucial for effective project schedule management.

What is a project schedule network diagram in project management?
  1. A document that lists all the stakeholders involved in a project
  2. A graphical representation of the logical relationships or dependencies among the project schedule activities
  3. A detailed cost estimate of the project
  4. A document that formally authorizes a project
B) A graphical representation of the logical relationships or dependencies among the project schedule activities

Unlock Full Course Access

Take the next step in your career—purchase now and master project management with our comprehensive PMP exam prep course!

Project Documents Updates

Imagine you're managing a project to launch a new product. As you start to sequence activities, you realize the importance of project documents such as activity attributes, activity list, assumption log, and milestone list. These documents play a crucial role in project management and may need to be updated during the process of sequencing activities.

For instance, if the design phase of the product takes longer than expected, you might need to update the activity list and attributes to reflect this change. This could also impact the assumption log, as your initial assumptions about the duration of the design phase would need to be revised.

Activity attributes describe the necessary sequences of events, defined predecessor or successor relationships, and logical relationships between activities, including defined lead and lag. These attributes provide a detailed understanding of each activity, aiding in the effective sequencing of project tasks.

Changes in relationships among project activities during sequencing activities may impact the activity list. For instance, if the sequence of certain activities changes, the activity list must be updated to reflect these changes.

The assumption log, which records assumptions and constraints, may also need to be updated based on sequencing, relationship determination, and leads and lags. For example, if a new constraint emerges during the sequencing of activities, it should be recorded in the assumption log.

Updates in the assumption log may give rise to individual project risks that could impact the project schedule. For instance, if a new assumption suggests a potential delay in a critical activity, this could pose a risk to the project schedule.

Reflecting on our product launch project, changes in relationships among project activities during sequencing activities may impact the scheduled dates for specific milestones in the milestone list. For example, if the sequence of activities leading to the design completion milestone changes due to the extended design phase, the scheduled date for that milestone may need to be adjusted.

In conclusion, updating project documents is a dynamic process that directly impacts the sequencing of activities and the overall project schedule.

Which of the following project documents is typically updated during the process of sequencing activities in project management?
  1. Project charter
  2. Activity attributes
  3. Project schedule
  4. Cost baseline
B) Activity attributes